Tanzanian Gold commissions expanded processing plant at Buckreef

Tanzanian Gold has commissioned an expanded processing plant which can process up to 360 tonnes per day at the Buckreef gold project.

The expanded processing plant was completed in October. Tanzanian Gold continued to operate Buckreef’s 120 tpd plant during construction. This processing plant, which has a 90% gold recovery rate, has now been incorporated into the new processing plant circuit.

The 360-tpd processing plant came in at expected cost of US$1.6 million, Tanzanian Gold said. The expanded plant will enable the company to produce between 750 and 800 ounces of gold per month, at cash costs averaging between US$725 and US$825 per ounce.

Tanzanian Gold has plans to advance a 1,000 and more tpd operation, which will produce between 15,000 and 20,000 ounces of gold per year. It is likely that additional mills and tanks will be acquired to be incorporated into the processing plant, chief executive Stephen Mullowney told Mining Magazine.

Expectations

Tanzanian Gold will spend additional revenues stemming from increased production on exploration and drilling, and enhanced CSR/ESG programs. The company has provided supplies for local schools, and future ESG programs will likely focus on this issue, Mullowney said.

Tanzanian Gold has commissioned an expanded processing plant which can process up to 360 tonnes per day at the Buckreef gold project. The expanded processing plant was completed in October. Tanzanian Gold continued to operate Buckreef’s 120 tpd plant during construction. This processing plant, which has a 90% gold recovery rate, has now been incorporated into the new processing plant circuit.

The 360-tpd processing plant came in at expected cost of US$1.6 million, Tanzanian Gold said. The expanded plant will enable the company to produce between 750 and 800 ounces of gold per month, at cash costs averaging between US$725 and US$825 per ounce.

Tanzanian Gold has plans to advance a 1,000 and more tpd operation, which will produce between 15,000 and 20,000 ounces of gold per year. It is likely that additional mills and tanks will be acquired to be incorporated into the processing plant, chief executive Stephen Mullowney told Mining Magazine.

Tanzanian Gold will spend additional revenues stemming from increased production on exploration and drilling, and enhanced CSR/ESG programs. The company has provided supplies for local schools, and future ESG programs will likely focus on this issue, Mullowney said.