Asante achieves key milestone with first mineralized material delivery from Russel Pit to Bibiani Process Plant in Ghana

Asante Gold Corporation, a gold production, exploration, and development company, has announced a major milestone with the successful delivery of the first mineralized material from the Russel Starter Pit to the process plant at the Bibiani Gold Mine in Ghana.

According to Dave Anthony, Asante Gold Corporation President and CEO, the achievement followed the company’s receipt of all necessary permits from Ghanaian authorities.

Located 3.8 kilometres from the Bibiani process plant, the Russel deposit contains 119,000 ounces of measured and indicated gold resources (open pit) at a grade of 1.80 grams per tonne, with mineralogy similar to the Bibiani Main Pit.

“This is the third satellite pit explored, defined and optimized by Asante since acquiring the Bibiani properties, and the start of production at Russel represents another successful milestone on our journey to grow Asante’s production to more than 500,000 ounces by 2028,” said Anthony.

“Approval for mining at Russel follows other major catalysts, including the re-routing of the Bibiani-Goaso highway, which will allow us to access additional oxide mineralized material, and further progress on the construction of the Bibiani sulphide treatment plant. Once fully ramped-up, Bibiani-Chirano will be the seventh largest gold producing district in Africa and the only Tier One Gold District in Africa held outside of a major gold producer,” he added.

Highlights

Ghanaian Owned Contractor Vuluxx Mobilized

Ghanaian owned and Bibiani based, Vuluxx mobilized its team to site during the month of May 2024 and commenced mine infrastructure development, including vegetation clearing, topsoil stockpiling, and preparatory work on the Russel haul road and laydown areas.  Vuluxx’s fleet will peak with five excavators sized with up to a total of 56 haul trucks and associated ancillary equipment. Vuluxx’s experienced management team has over 24 years in the industry and Asante is excited to be working with another local Ghanaian contractor.

Project Details

The Russel Starter Pit will operate for the first 15 months and will immediately be followed by Russel cut 2. It is projected to deliver a total of 1.9Mt at 1.62g/t over a period of 30 months to the Bibiani process plant.This material will supplement production from the Main Pit oxides, which have been unlocked after the recent diversion of the Bibiani-Goaso highway (see press release dated June 13, 2024).

The Russel Starter Pit is just over 390 metres in strike and will reach a depth of 168 metres from surface. Pit slope design parameters are consistent with those determined by the international consulting group SRK. Oxidation reaches a depth of 60 metres, transitioning to sulphide mineralization from 80 metres. It is anticipated that the pit can be excavated without the use of explosives to a depth of 50 metres.

The mining contractor will provide all mining services including waste removal and transportation of mineralized material to the ROM pad.

Asante is in the process of extending the known Russel resource down plunge and along strike to the south. Current drilling is anticipated to not only convert inferred mineralization but to confirm the suitability of the resource for underground mining methods. A preliminary study into the potential transition to underground mining at Russel will be undertaken in line with Asante’s strategy.